AIRPORT LAYOUT PLAN.
Airport Layout Drawing
Airport Staging
The Airport Layout plan depicts the existing airport
facilities as well as the recommended
facilities required to accommodate forecast demand through the Year 2025.
Major airfield
improvements incorporated in the ALP are summarized as follows:
1. Construct new commuter terminal area
2. Construct parallel taxiway Runway 9/27
3. Construct new maintenance/storage hangar/general aviation
terminal building expansion
4. Construct new t-hangar/storage complex
5. Expand general aviation apron
6. PAPI-2 Runway 17/35
7. Construct ARFF Building
8. Air Traffic Control Tower |